BeCOMS® – Pre-Commissioning Checks

Check for the following:

  • 1. correct wiring as given in Chapter 12 Appendix, see Fig. 12.1-12.4
  • 2. correct power supply on Evaluator
  • 3. Evaluator display is on

  • 4a. correct power supply on RS-485 converter
  • 5a. green power light on
  • 6a. the RS-485 converter rate setting is correct

  • 4b. PCI card is built into the PC correctly
  • 5b. PCI card driver for the corresponding OS is correctly installed
  • 7. COM-Port of the computer is correctly assigned
Information

Note: Steps 4a – 6a are required if a RS-485 converter is used; steps 4b – 5b are for the case when a PCI card is built into the PC.